Arbitration is a private, contractual form of dispute resolution. It provides for the determination of disputes by a third party arbitrator or arbitration panel, selected by the parties to the dispute. Disputes are resolved on the basis of material facts, documents and relevant principles of law.
The arbitration process is administered by an appointed arbitrator subject to any relevant contractual rules and subject to the statutory regulatory framework applied by the domestic courts. There are only limited rights of appeal and legal costs are usually awarded to the successful party.
English law does not insist on any formal requirements for an arbitration agreement (for example it can be verbal), however if the agreement is not in writing it will be outside the supervisory regime of the courts established by the Arbitration Act.
Arbitration clauses are traditionally found in all standard form contracts used in the UK, often with related adjudication clauses (for example, JCT 16, and ICE 7th Edition (now withdrawn in favour of NEC3)). In the last few years there has been a tendency to set the dispute resolution default at litigation rather than arbitration, leaving the parties to specifically agree to arbitration.
Arbitration commences with a notice to concur which provides for agreement on the appointment of an arbitrator, failing which an arbitrator may be appointed by a nominating body (which should be named in the contract). Arbitration is now usually combined with adjudication and mediation in tiered dispute resolution procedures.
For information on the process of arbitration, see How does arbitration work?
Advantages:
- It is private - there is no public record of any proceedings, although not necessarily confidential.
- Speed, although this depends very much on the manner in which the arbitrator conducts the arbitration.
- The parties can agree on an arbitrator with relevant expertise in the matter. The arbitrators award can be enforced as a judgement of the court.
Disadvantages:
- The parties must bear the costs of both the arbitrator and the venue.
- Sometimes arbitration simply mimics court processes and so you do not get the advantage of informality and speed.
- Limited powers of compulsion or sanction if one party fails to comply with directions of the arbitrator, which can significantly slow down the process.
- The arbitrator has no power to make interim measures, such as for the preservation of property.
- Limited appeal rights.
For information on becoming an arbitrator, see How to become an arbitrator.
[edit] Related articles on Designing Buildings
- Adjudication.
- Alternative dispute resolution.
- Alternative Dispute Resolution legislation.
- Arbitration Act.
- Arbitration panel.
- Arbitration v Adjudication.
- Breach of contract.
- Causes of construction disputes.
- Conciliation.
- Construction Industry Model Arbitration Rules CIMAR.
- Contract claims.
- Dispute resolution.
- Dispute resolution boards.
- Dispute resolution procedure.
- Evaluation of claims.
- Expert determination.
- Expert evaluation.
- Housing Grants, Construction and Regeneration Act.
- How does arbitration work?
- How to become an arbitrator.
- Joinder.
- Mediation.
- Pay now argue later.
- Pendulum arbitration.
- Provisional relief.
- The role of the mediator.
- Scheme for Construction Contracts.
- Without prejudice.
[edit] External references
- ICE contract.
- JCT contract.
- FIDIC contract.
- JCT/CIMAR: Construction Industry Model Arbitration Rules.
- PACE: Guide to the Appointment of Consultants and Contractors P549 and 384
Featured articles and news
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.
Independent Building Control review panel
Five members of the newly established, Grenfell Tower Inquiry recommended, panel appointed.
Welsh Recharging Electrical Skills Charter progresses
ECA progressing on the ‘asks’ of the Recharging Electrical Skills Charter at the Senedd in Wales.
A brief history from 1890s to 2020s.
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.